EMBER - Project Update

EMBER started in May 2001 (Month 1) and will go on until April 2003 (end of Month 24).


  • WP1, WP2 and WP3 have been completed.
  • WP4-WP7 are probably the most important workpackages of the whole project, since they involve the finalised version of the textbook, website and CD-ROM.
  • WP9 is an ongoing workpackage that covers the whole length of the project.

    Please click on the grey-shaded areas above to view a description of the project's Workpackages (WP) and completed Deliverables (D).